progress

Progress

Project Photos

  • Permian Basin Behavorial Health Center May 2025 Progress 2Permian Basin Behavorial Health Center May 2025 PBBHC Construction Site March 2025PBBHC Construction Site February 2025PBBHC Construction Site February 2025PBBHC Construction Site January 8, 2025PBBHC Construction Site October 2024PBBHC Construction Site July 2024PBBHC Construction Progress June 2024 -3PBBHC Construction Progress June 2024 -2PBBHC Construction Progress June 2024PBBHC Construction Progress May 2024 -2PBBHC Construction Progress May 2024PBBHC Construction 3/22/2024PBBHC Construction Progress Photo 3.7.24PBBHC Construction 02/22/24Exterior Building ViewParking lot building viewCourtyardBluePrint

Project Schedule

Projected Operational Date

April 2026

PBBHC Drone Footage 08/09/24

August 2024

PBBHC Drone Footage 06/10/2024

June 2024

PBBHC Drone Footage 05/03/2024

May 2024

PBBHC Drone Footage 02/22/24

February 2024

Final Construction Documents Completed

December 2023

Encumbrance Deadline For Initial $40M Appropriation

November 2023

Construction Period

10/31/23 - 10/15/25

October 2023

Groundbreaking Ceremony

April 2023

Site Acquisition Completed

Through public/private partnership and cooperation among multiple distinct communities, the Permian Basin Region will set the standard for behavioral health care in Texas and New Mexico.

December 2022